We have been offering dedicated medical and nursing writing services to nursing students for several years. Our nursing papers are meticulously crafted to meet the highest academic standards and adhere to the prescribed referencing formats, including APA, MLA, and Chicago style. Our team comprises seasoned nursing writers who possess extensive knowledge and expertise across a wide range of nursing topics. Whether it’s assignments, research papers, case studies, literature reviews, or any other task, our writers are well-equipped to handle them proficiently.
CON 4000 Term Project
Summer 2019
Project due July 1
st
.
Page 1 of 4
1) Background: You have just started working for XYZ General Contractors. XYZ has recently been
awarded the Lake Washington Surface Water Treatment Plant Office Staff/Shop Building project by
the City of Melbourne, FL. As the project manager you have three major tasks. Each task is explained
in detail in paragraphs 2 through 5.
a) Task I – develop your schedule to deliver the term project (submit as HW 8).
b) Task II – develop the term project deliverables.
c)
Task III – prepare a 5 minute briefing for the XYZ owners and/or building owner (City of
Melbourne). You will have different briefing topics. Make sure that you use the correct topic
(Paragraph 4.e. below).
2) Task I – develop your schedule to deliver the Term Project (HW 8)
a) Check out for special topics assigned to you (Paragraph 4.e below).
b) Develop a schedule for delivering the term project including:
i)
CPM Network showing activities and logic
ii) Resource assignments (you)
iii) Milestones
c)
See HW 08 for details.
3) Task II – develop your schedule for the Lake Washington Project
a) Contract award date: September 2, 2019, total contract amount $479,000.
b) NTP date: September 30, 2019
c)
Contract completion date: April 7, 2020
d) Create activity list
i)
During the time between the contract award date and the Notice to Proceed date you have
provided bonding, financial data, safety plans, etc. to the City for approval. You also started
the permitting process. You do not have to include time for permitting etc. in your schedule.
Your schedule start date is the NTP date. The explanations here are given to you just to give
you an idea what must be done between contract award and actual start date.
ii) Inspections must be included in your schedule
(1) Fire sprinkler system
(2) Electrical and plumbing before drywall
(3) Electrical, plumbing, mechanical above ceiling before installing ceiling tiles
e) Estimate durations
i)
Submit an estimating sheet showing duration calculations for tasks designated on the draft
task list as “estimate required.â€
ii) You have the total cost of the contract based on your winning bid. You must distribute the
total cost among activities in a reasonable way but you do not have to do any detailed cost
estimates.
f)
Create an MS Project schedule
i)
Project start date: NTP date
ii) Construction start date: NTP date
iii) Include milestones for:
CON 4000 Term Project
Summer 2019
Project due July 1
st
.
Page 2 of 4
(1) Contract award
(2) NTP
(3) Demolition complete
(4) Foundation and underground utilities complete
(5) Building closed in (exterior complete)
(6) Building interior complete
iv) Include summary tasks for:
(1) Entire project
(2) Site work
(3) Demolition
(4) Shop
(5) Maintenance Office
v) Create an early start cost S-curve for the project similar to Fig 15.7. Label the x-axis of the S-
Curve in months (not quarters or weeks) so that it will match monthly pay requests.
g) Prepare selected reports before any work is done that you will use to manage the project.
i)
Network Diagram
(1) Format nodes like this:
(2) Make the network legible
ii) Bar Charts
(1) PM’s Bar Chart
(2) Owner’s bar chart
(3) Subcontractor bar charts (Demolition and Plumbing)
(4) Superintendent’s 3 week look-ahead for the start of week 2.
4) Task III –Presentation: Prepare a 5-minute PowerPoint presentation that included items a through d
below, and your assigned topics in item 4e below.
a) Introduction
b) Explanation of the purpose of the presentation
c)
A project schedule in bar chart format
d) An S Curve for project cost vs. time
e) Information required by the special topic below:
i)
Topic 1: Initial schedule submission meeting. You are meeting with the Owner’s
Representative from the City Engineer’s Office to go over your project schedule. Your
project progress payments will be made based on the approved schedule. Your objective is
to show a well thought-out schedule in both bar chart and tabular format. Since the
audience for this presentation is the building owners, use LS/LF dates. Also show the
payment S Curve for the project.
ii) Topic 2: Your schedule was approved. The contract allows you to receive monthly progress
payments by calendar month. It is the end of the first month of the project. Prepare the first
payment request. All project activities are on schedule (ES/EF). The contract specifies that
ES
LS
Dur
Float
Name
EF
LF
CON 4000 Term Project
Summer 2019
Project due July 1
st
.
Page 3 of 4
payment requests include a bar chart schedule showing progress updates and a tabular
section with the following information for all schedule activities:
Activity
#
Name
Activity
Value $
Plan
Start
Plan
Finish
Actual
Start
Actual
Finish
%
Compl
Prev
Pay
Pay
Req
iii) Topic 3: Progress presentation week 8 (Nov 26th). You were on schedule through the end of
week 7, however a storm stalled over Melbourne for the past 7 days stopping all exterior
work. Explain the impacts to the owner. The contract allows for weather delay extensions to
the contract completion date but does not allow for additional payment for weather delays.
In your presentation show a bar chart schedule with the original baseline schedule and
revised schedule with weather delay. Show a new S Curve for the project.
iv) Topic 4: You are preparing an XYZ Construction internal progress presentation at the end of
week 3. You encountered an unknown underground concrete foundation underneath of the
concrete towers that you demolished as part of the contract. The unknown foundation
consisted of a 30 foot diameter concrete ring wall 18 inches thick by 5 feet deep. The ring
wall will have to be removed and the area inside the ring wall will have to be backfilled. You
estimate that bringing in and placing compacted fill will be a direct cost of $13,000. Estimate
how long it will take to remove the concrete and place the fill. In your presentation to the
XYZ management explain the impacts of this unknown site condition on your schedule and
what you believe should be done about it.
v) Topic 5: Prepare a progress presentation through week 8 to the City of Melbourne. You are
on schedule but the City has just notified you that they want to change to a different type of
roll-up door. The original door has already been shipped. You can return it for $500
shipping plus a $1,000 restocking fee. The new door costs $4,000 more than the door
originally in the specifications. It will take 18 days to receive the new door from the date
that you order it. In your presentation explain the effects of this change request on the
project schedule and present alternatives including additional cost to stay on the original
schedule or additional time and cost if the project delivery date is delayed.
vi) Topic 6: Your schedule was approved. It is the end of the second month of the project. The
contract allows you to receive monthly progress payments. Prepare the second payment
request. All project activities are on schedule (ES/EF). Assume that you were on schedule at
the end of the first month and that you were paid the “Previous Pay†amount at the end of
the first month. The contract specifies that payment requests include a bar chart schedule
showing progress updates and a tabular section with the following information for all
schedule activities:
Activity
#
Name
Activity
Value $
Plan
Start
Plan
Finish
Actual
Start
Actual
Finish
%
Compl
Prev
Pay
Pay
Req
CON 4000 Term Project
Summer 2019
Project due July 1
st
.
Page 4 of 4
vii) Topic 7: You are preparing an XYZ Construction internal progress presentation. The project
was on schedule until you started excavation of the new Maintenance Office footers. On
the first day of excavating for the footers you encountered an unknown underground 6 inch
cast iron water line. After consulting with the City of Melbourne engineer, you have been
directed to relocate the line so that it does not go under the new building. Your estimating
staff provided a cost of $4,500 based on previous subcontracts for this kind of work.
Complete a detailed estimate sheet showing the duration required to cut the existing line,
pump grout into the abandoned pipe under the new building, excavate, install, and backfill
approximately 110 feet of new 6 inch cast iron line around the new building footprint. In
your presentation to the XYZ management explain the impacts of this unknown site
condition on your schedule and what you believe should be done about it.
viii) Topic 8: Your schedule was approved. It is the end of the fourth month of the project. The
contract allows you to receive monthly progress payments. Prepare the fourth payment
request. All project activities are on schedule (ES/EF). Assume that you were on schedule at
the end of the first, second and third month and that you were paid the “Previous Payâ€
amount at the end of the third month. The contract specifies that payment requests include
a bar chart schedule showing progress updates and a tabular section with the following
information for all schedule activities:
Activity
#
Name
Activity
Value $
Plan
Start
Plan
Finish
Actual
Start
Actual
Finish
%
Compl
Prev
Pay
Pay
Req
5) Include a cover sheet and contents page for your written submission. Submit your MS Project
schedule and PowerPoint presentations on Canvas by the due date with your written submission
described under 3). Additional specific guidance will be provided during class and computer lab
periods.
We have been offering dedicated medical and nursing writing services to nursing students for several years. Our nursing papers are meticulously crafted to meet the highest academic standards and adhere to the prescribed referencing formats, including APA, MLA, and Chicago style. Our team comprises seasoned nursing writers who possess extensive knowledge and expertise across a wide range of nursing topics. Whether it’s assignments, research papers, case studies, literature reviews, or any other task, our writers are well-equipped to handle them proficiently.
Do you need a similar assignment done for you from scratch? We have qualified writers to help you. We assure you an A+ quality paper that is free from plagiarism. Order now for an Amazing Discount!
Use Discount Code "Newclient" for a 15% Discount!
NB: We do not resell papers. Upon ordering, we do an original paper exclusively for you.